1
PROJECT HIGHLIGHTS
 
 
Project Name Marine Science and Technology Center
Project Owner Highline Community College
Project Architect Mulvanny G2
Project Location Redondo Beach, WA
   
Project Start Date July 2007
Project Competion Date January 2008
   
Project Size 4200 sq ft
   
Project Description
ATC will renovate an old educational facility and hardhat dive shop, transforming it into Highline Community College’s new Marine Science and Technology Center. This project will consist of complete demolition of all buildings on the pier followed by a build-up of wood frame buildings that replicate a traditional Cape Cod light house. The new pier will be equipped with classrooms, laboratories and a working aquarium.
 

Pictorial Diary

07-24-07 Pre-Construction



08-22-07 Demolition


10-05-07 Construction

12-05-07 Construction

12-19-07 Construction

sitemap
feedback
terms of use
privacy
websites
ATC © 1999, All rights Reserved
web design by SilverAngel Productions